This program holds the number of days it takes to move goods between internal locations.

The routine is only required if it takes more than a day to move goods between locations. i.e., Internal transfers.

The start point is the beginning of the journey, with the end point being the destination. Do not generate separate timings for drop-off points as SwanFRS creates the transfer as a single process - A to X and not A to Z via C

Menu Location: System Admin > Warehouse > Set Up Transfer Timings

The routine requires selection of a Location from a pick list and then displays the vehicles assigned to that location. This location is the journey start point.

  • Click the NEW button or New on the side panel to generate a new record.

  • Click the icon to amend an existing record.

  • Once in amend / insert more, click the to save changes or to abort the action.

  • Click the CLOSE button, or Back option on the side panel to leave the page (or select another option from the menu)

Item

Description

Destination Location

Choose a destination location from the pick list.

This forms the end point of the transfer, with the start point being the location selected at the top of the page.

Transfer Days

Specify the number of days, (elapsed days including weekends) it takes to move goods from source to destination.

Files from the Confluence page

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article