This optional feature, enables restrictions to be placed on when and if a purchase order can be ‘adjusted’ post sending to the supplier.
It is possible to set grace periods relating to purchase orders for amendment, additions, and cancellations.
The system allows the specification of the number of days after the PO is communicated to the supplier, the supplier will allow amendment of the PO composition. Similar settings are available controlling the time new requirements can be added to the PO and the time the supplier will allow items on the PO to be cancelled. Where not set the system, defaults will apply.
Menu Location: System Admin > Purchasing > Set Up Supplier Purchase Order Terms
|
Item |
Description |
|
Supplier |
The name of the supplier. |
|
Amendment Days |
Specify how many days after ‘sending’ the purchase order to the supplier, it is possible to amend the composition of the purchase order. Leaving blank or setting to zero blocks this feature. This relates to changing the option combinations. |
|
Amendment Lead Time |
Specify if the clock restarts or continues to tick once an amendment has taken place.
|
|
Addition Day |
Specify how many days after ‘sending’ the purchase order to the supplier, it is possible to add new SKUs to the purchase order without the need to cancel and re-create the purchase order. Leaving blank or setting to zero blocks this feature. This relates to changing the option combinations. |
|
Addition Lead Time |
Specify if the clock restarts or continues to tick once an addition has taken place.
|
|
Cancellation Days |
Specify how many days after ‘sending’ the purchase order to the supplier, it is possible to cancel a line on the purchase order without having to take receipt of the stock. Leaving blank or setting to zero blocks this feature. This relates to changing the option combinations. |
|
Cancellation Lead Time |
Specify if the clock restarts or continues to tick once line cancellation has taken place.
|
Files from the Confluence page
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article